The Halifax Convention Centre just opened its doors and it’s already costing the city far more than initial estimates.

New financial figures are projecting that a planned $1.8-million shortfall in the city’s HCC reserve fund has now nearly doubled to $3.5-million.

Worse still, a projected $6-million surplus after 10 years of convention centre operations has now drastically and severely fallen to an $18-million deficit.

Those numbers are a best-case scenario provided assessment values start to recover in five-to-seven years time.

Credit: VIA HRM

The HCC—part of the larger Nova Centre complex—reached substantial completion last month after years of construction delays. It’s leased by the province from Joe Ramia, with HRM covering half of the annual rent payments.

In order to offset that cost and other operating expenses, HRM created a reserve fund several years ago within which it dumps all the commercial property taxes from the entire Nova Centre.

Initially, it was hoped those taxes would be enough to fully cover HRM’s half of the annual payment by year six of Convention Centre operations. As time went on, more tenants would be signed for the Nova Centre and the property’s assessment would go up, leading to a healthy surplus in the reserve fund.

But when the original plan was approved in 2010, there wasn’t any other office construction underway in the downtown core. Things have changed.

“Since 2010 there has been considerable office construction in downtown Halifax leading to higher vacancies than expected and downward pressure on office leases,” reads the staff report out of HRM’s Audit and Finance committee. “Hence, rather than assessments growing as expected, assessments in the downtown office market have declined.”

The current assessed value of the Nova Centre property is $200 million. The municipality is appealing that figure, but in the interim, it means HRM is taking in $900,000 less this year in tax money. Combined with increased operating costs and other HCC expenses, that equals out to the $3.5-million shortfall.

“While the economy remains strong, it is extremely difficult to ascertain when assessments for the downtown office market will again start to rise,” writes staff—meaning the reserve won’t be showing a surplus anytime soon.

“In the next two to four years there may be a reserve shortfall of between $5 million to $8 million.”

The city covers capital costs, debt and interest in its annual payments, while also cost-sharing the operational costs Events East spends in managing the new convention centre.

The operating costs this year for the HCC are projected at $6.4 million. The province handles most of that, while Halifax is only on the hook for its half of the annual lease payment, plus any expenses since substantial completion a month ago. That works out to $645,000.

But additional capital and “smallware costs” yet to be determined could increase the final figure by as much as $1.5 million.

To counter the financial sinkhole, staff are suggesting any deed transfer tax money from property sales within the Nova Centre will now also go into the HCC reserve account, along with money from the city’s general surplus (if needed).

The staff report—which will be discussed Tuesday by council—also recommends paying off the $301,500 in extra expenses the province says HRM owes.

But otherwise, things are fine.

“The new Halifax Convention Centre is currently exceeding expectations for convention bookings,” say staff. “The facility shows every sign of being extremely successful and contributing to the economic and cultural life of the province.”

Related Stories

Customers of the state

The myth of “your tax dollars at work” and why government shouldn’t be treated as a corporation.

Join the Conversation

6 Comments

  1. Really? No one saw this coming?

    It appears obvious that the powers that be did not have the intelligence to predict this scenario, even with the reams of office vacancy information in the available in the public domain for several years; or that a simple drive through the streets of the city would have revealed.

    In truth, they were the only people who did NOT see this coming while they blindly foisted this ridiculous boondoggle upon the citizens of Halifax under the false premise of progressive action – thus, leaving the rest of us, as usual, to pay for their mistakes.

  2. Extremely successful, except in the sense it loses money each and every year to the tune of 18 million dollars in 10 years.

    If it were my business venture, I wouldn’t consider that success.

  3. 18 milion is just what the HRM taxpayer’s are paying for, that does not include what taxpayer’s are paying provincially every year. Not to mention we have paid for it to be built in the first place! Then we have to pay to lease back what we paid to build for 25 years, we then have to sign an additional five year lease and finally at the end of those 30 years tax payers will finally own what they will have paid for multiple times over for!
    Still waiting for someone to explain to me how this was good for taxpayers! So far it was only good for Joe Ramia!!

  4. Developers make money out of developing, whether what they develop is feasible or not. There are many examples of this in other cities around the world with housing and office gluts. Once the banks, governments or other organizations are on the hook for the money, the developers are flogging their best new development and everybody has to pony up because if not the developers may have to go into bankruptcy. It’s kind of like ” the art of the deal”.

  5. Maybe a CFL stadium will fix the problem. Can’t wait to start paying for the next brilliant government mistake!

Leave a comment

Your email address will not be published. Required fields are marked *