Washmill underpass: follow the money

Which companies are benefiting from cost overruns?

Posted By on Thu, Feb 10, 2011 at 8:53 AM

overpass1.jpg
As we detailed two weeks ago, the Washmill underpass project, originally projected to cost $10 million, is an astonishing $8 million over budget. So far, $9,656,252 has been spent on the roadway, which now leads directly into a stone wall. The money needed to complete the road has yet to be allocated, but here’s who has been paid so far:

Maritime Testing---environmental monitoring and slate management, $37,364.
Servant Dunbrack---surveying, $12,205.
SNC Lavalin---design work, wetland alteration application, construction inspection, $202,140 spent, with another $129,710 budgeted, for a potential total of $331,850.
Brycon Construction---Phase 1 construction (detour road base, water retention, excavation), $3,199,637.
Dexter Construction---Phase 2 construction (detour road paving, bridges, storm water piping), $6,456,615, with another $1,672,975 still budgeted.

Phase 3 construction consists of building the actual Washmill Boulevard and associated sidewalks, lighting and landscaping. Supposedly, this will cost somewhere in the range of $5-7 million, but full costs won’t be known for several weeks.

Tags:

Comments (6)

Showing 1-6 of 6

Add a comment

 
Subscribe to this thread:
Showing 1-6 of 6

Add a comment

Remember, it's entirely possible to disagree without spiralling into a thread of negativity and personal attacks. We have the right to remove (and you have the right to report) any comments that go against our policy.

Coast Top Ten

Opinionated

More »

Reality Bites

More »

Shoptalk

More »

In Print This Week

Vol 25, No 4
June 22, 2017

Cover Gallery »


Real Time Web Analytics

© 2017 Coast Publishing Ltd.